Trevor Johnson, Author at Maryland League of Conservation Voters Education Fund

About Trevor Johnson

This author has not yet filled in any details.
So far Trevor Johnson has created 32 blog entries.

PJM and Maryland – Issues and Challenges

Introduction

PJM Interconnection (PJM) is the country’s largest regional transmission organization, serving 67 million customers across Maryland and all or parts of 12 other states and Washington, D.C. While local utilities own and operate distribution equipment (i.e., poles and wires), and energy companies own generation in Maryland, it is PJM that is ultimately responsible for the reliable operation of the grid. PJM also runs wholesale energy markets, plans the high-voltage transmission network, and manages the interconnection queue for new generation projects. So while Maryland, through legislation and state regulatory agencies, must review and approve utility rates and spending, as well as the type of generation built in state, PJM manages the electricity markets which set prices for project developers, as well as the planning and approval process for transmission to connect generation to the grid. These roles give PJM authority over what energy projects are built, how reliable electricity is, and how much electricity costs.

Governance

PJM is a private organization, and its operational rules, which govern its energy auctions, are set by its board and voting stakeholder members. The majority of stakeholder members are the for-profit companies (transmission and generation owners, as well as utilities) that operate in PJM’s footprint. Although there is some limited voting representation in the stakeholder process for Marylanders –  through the Office of People’s Counsel (OPC) – this vote is diluted compared to industry, especially in lower-level stakeholder committees1 in which affiliate voting is allowed. For example, where OPC might have one vote in a lower-level committee, Exelon Utilities would have 6 total affiliate votes – 3 of which are represented by Maryland utilities: BGE, Pepco, and Delmarva Power and Light. Maryland’s other venues for influencing, albeit not voting at PJM – include its membership in the Organization of PJM States, inc. (OPSI), and recently the State Legislators Collaborative, the National Caucus of Environmental Legislators, and the PJM Governors Collaborative2. These groups have been instrumental in pushing for governance reform at PJM – decisions made at the Federal Energy Regulatory Commission (FERC) – as well as securing a price cap for PJM’s capacity market, which is estimated to have saved at least $13 billion in costs from being passed along to ratepayers in PJM in a given year.

Energy Generation: Gaps and Misplaced Priorities

While the Maryland Public Service Commission (PSC) officially approves building new energy generation projects through Certificates of Public Convenience and Necessity (CPCN), and the legislature directs the state’s energy mix priorities (e.g., directly through procurement targets such as the POWER Act, or provisions of the Utility RELIEF Act), PJM heavily influences what facilities can actually be built. Proposed projects must secure an interconnection agreement from PJM and pay for any upgrades needed to connect them to the regional transmission grid. Further, PJM controls the mechanisms that send economic market signals to generation developers. PJM’s rules have delayed clean energy deployment, with approximately 285 gigawatts (GWs)  of clean generation attempting, and failing, to receive an interconnection agreement since 2020. At the same time, PJM rules have fast-tracked new gas generation—including in Maryland through its Resource Reliability Initiative (RRI). Moreover, PJM has applied to run a secondary “fast track” process called the Expedited Interconnection Tract (EIT), which, similar to the RRI, heavily favors developers of new gas power. PJM sets the rules for these processes (see Governance section above), which have prioritized development of generation with high capacity factors (i.e., facilities that are available 24/7/365), as determined by the PJM-assigned Effective Load Carrying Capacity (ELCC) value. These rules penalize cleaner, cost-effective, and faster-to-construct generation alternatives while prioritizing fossil fuels.

Moving forward, if the rules stay the same, battery energy storage systems could be the beneficiary of rules prioritizing capacity because of the immense benefits they bring to the grid because of their comparatively low cost and build time for a high-capacity value asset. Unlocking storage’s full potential for both reliability and affordability means pairing it with clean and renewable energy on the grid.

Load and Reliability

PJM is seeing rapidly surging load growth, the vast majority of which comes from large load additions – i.e., data centers – and threatens the clean energy transition, ratepayer affordability, and reliability.

Ratepayers can already feel the effects. PJM conducts regular capacity auctions, where it secures promises from power suppliers to provide enough energy resources for the future. Rising demand has made it more difficult for PJM to meet its needs, resulting in record-high auction prices, prices that would have been substantially higher but for the negotiated price cap. These prices translate to higher electric bills for utility customers. More concerningly, for the first time ever, PJM missed its reliability target in capacity auctions held in December 2025 and July 2026 for delivery years3 2027/2028 and 2028/2029 – meaning there is an increased risk PJM won’t be able to secure energy to meet the region’s needs. PJM has a potential generation output of approximately 182 GW, but not all of it is available at all times due to outages, maintenance, etc. In 2026, PJM hit a record for peak summer demand of 168 GW, of which about 6 GW was met by demand response programs.

Despite being within its reliability target for this delivery year, PJM has turned to an emergency posture multiple times in 2026, directing the use of non-economic dispatch (i.e., expensive generation) and securing numerous 202(c) orders from the Department of Energy under the Federal Power Act, which allows for the use of emergency generation and is not subject to any federal or state environmental regulatory controls. Five of these orders allowed PJM to direct data centers to disconnect from the grid and run their backup generators on emergency footing (not subject to runtime or environmental rules). In aggregate, this raises serious questions about how new large-load systems will be integrated into the grid – both in Maryland and in PJM broadly.

PJM is facing difficult decisions with large loads coming online, or at least being forecasted to come online, faster than anyone anticipated. They are trying to set up the structure to bring more capacity online to meet this demand. The rules set by PJM, whose voting members are overwhelmingly incumbent energy generators and utilities, and operationalized through its interconnection structure and fast-track queues, currently benefit gas over clean energy like solar. This is contrary to what Marylanders need, which is more electrons on the grid right now. Clean energy paired with storage is the fastest, most cost-effective option to provide least-cost reliable electricity to Marylanders.

This content was prepared for the Bright Future Maryland Coalition by the Center for Progressive Reform and Maryland LCV Education Fund.

MORE:

Maryland LCV and partners PJM press conference in May 2026.
Baltimore energy advocates press PJM over data center costs, WBAL News Radio
Maryland leaders call for reforms within regional grid operator amid annual conference,
WYPR
Governor, lawmakers call for reforms at PJM to lower energy bills, Fox TV 45
Maryland lawmakers press electric grid operator on skyrocketing bills
, Baltimore Banner


1: As a rough analogy, in PJM’s governance process, stakeholder committees operate not dissimilar from legislative committees or subcommittees; actions there are not final, but have a strong impact in shaping what policies and initiatives make their way up to voting or board action that will be put into effect.

2: Maryland representatives and agency heads have, in the last year, taken strong leadership positions in engaging with PJM through OPSI, the legislators’ collaborative, and the National Caucus of Environmental Legislators. Governor Moore has also been extremely active within the context of the governors’ collaborative.

3: A delivery year runs from June 1 of the starting year through May 31 of the ending year. Currently, we are in the 2026/2027 delivery year.

2026-11-03T15:53:48-05:00October 26th, 2026|Categories: Clean Energy & Energy Efficiency|

Faith Communities Weigh In on Data Center Development in Baltimore County

By: Joshua Long and Joelle Novey, as shared with the Maryland League of Conservation Voters Education Fund

The opinions shared in this piece are those of the speaker and/or the person being featured in the story. They do not necessarily reflect those of the Maryland League of Conservation Voters Education Fund.

Joshua Long is an environmentalist, a songwriter and musician, a public theologian, an entrepreneur, and the congregational organizer for the environmental non-profit Interfaith Power & Light. With a background in several Christian denominations, interfaith work, and Unitarian Universalism, Josh brings a pluralist theological perspective. At the Wesley Theological Seminary, Josh developed a musical thesis on climate and faith that explored how sacred music can foster spiritual experiences and build communities of hope and justice. He feels called to care for Creation.

Joshua Long playing a guitar

This call has most recently brought him to work on data center development near his home in Baltimore County, where he grew up and now is raising his family. As a parent, he is worried that the infrastructure and energy demand from data centers are driving increasing energy costs for families across Maryland. He is also worried about the potential for pollution in nearby waterways and the noise and heat island effects that further diminish safe outdoor play areas for his children in an already increasingly dangerous climate. When he organizes in communities, Josh takes his cues from his faith, whose leaders put everyday people and poor communities first. When he sees voices of his fellow neighbors being suppressed, he feels compelled to speak out, so he is angry about the environmental injustice of proposing any data center in neighborhoods where so many Black and immigrant families live.

“My faith teaches of our shared original blessing, that we are all made in the divine image, that every human being has inherent worth and dignity. And my experience of growing up in Baltimore County was one of being blessed by living and learning in a multiracial, multi-faith community.”

– originally published in an OP Ed in the Baltimore Sun

Josh contends that it is not AI that is deciding to place data centers in overburdened Black and brown communities; it is people who hope to profit from it. He is glad that widespread public concern led the Baltimore County Council to pause data center development for a year while the Planning Board conducts a study and prepares a report. As Josh sees it, too often, people talk as if he and his neighbors won’t really have a say in decisions about what gets built in their neighborhood, and no voice in how land, air, or water is used. But just because a technology exists doesn’t mean we don’t still have real choices about what to do with it.

“I’m not anti-AI or anti-tech; I’m pro-human, I’m pro-community, I’m pro-earth, and that includes all of creation, including all human beings… As a parent, I am asking that any data center bring real, tangible benefits to my family and to my neighbors. There are more sustainable ways to implement tech, and the county’s data center policy should revolve around them.”
– excerpt from Josh’s comments at a May 21st Baltimore County Planning Board meeting

2026-10-22T14:34:03-04:00October 22nd, 2026|Categories: Environmental Justice Story|

Energy Glossary

Energy Glossary

This glossary provides an overview of terms frequently used in the energy sector. The information is meant to be a guide for decision-makers and the public to better decipher these terms, which are often used in hearings, presentations, and other public fora without additional background or context. The terms provided in this glossary are presented by sector and may refer to definitions in other sectors. Keep this glossary handy to better understand wonky energy conversations.
If you have questions about this content or suggestions for additions, please contact Rebecca Rehr, Maryland’s Director of Climate Policy & Justice at info@mdlcv.org.

Electric Grid & Utility Operations
Renewable Energy & Demand Side Management
Utility Regulation & Markets
Emerging Technologies & Policy Concepts

Electric Grid and Utility Operations

  • Behind-the-Meter (BTM): Usually smaller energy resources that are located on the customer side of an electric utility’s meter and primarily used to serve or manage that customer’s energy needs. Depending on the technology, these resources may generate or store electricity, reduce or shift energy consumption, provide backup power, and sometimes export electricity to the grid. Examples include rooftop solar, battery storage, backup generators, programmable thermostats and other controllable equipment, and geothermal heat pumps.
  • Co-located/ Dedicated Generation: A power plant or other electricity generating resource that is built at or near a large energy user, such as a data center, and is intended to serve or offset that user’s energy needs. Co-located generation is often used as part of a “bring your own energy” model, in which the customer supplies some or all of its needed electricity rather than relying on the existing utility grid. These resources may or may not be BTM, depending on their configuration and point of interconnection, as well as any specific rules for large load users bringing their own energy.
  • Distributed Energy Resources (DERs): Energy resources that generate, store, or manage electricity on the distribution grid. All BTM energy resources are DERs, but not all DERs are located BTM on the customer’s side of the utility meter. For example, residential rooftop solar is a DER that is BTM, while a community solar project that households subscribe to is a DER that is in front-of-the-meter (defined below).
  • Distributed Generation (DG): Electricity produced by systems connected directly to the distribution grid or located behind a customer’s meter. DG refers to the electricity-generating subset of DERs and includes technologies such as rooftop solar, community solar, small wind, and on-site generators. While much smaller than traditional, centralized power plants, DG resources reduce reliance on long distance transmission and can defer the need for additional, costly grid infrastructure because they are located at or near where electricity is used.
  • Distribution Grid: The local network of power lines, poles, transformers, and substations that deliver electricity from the larger transmission systems directly to Maryland homes and businesses. The electric grid can be compared to a road network: If the transmission system (defined below) functions as an interstate highway, while the distribution grid is the network of local roads after you take the exit. The transmission system is overseen by the regional grid operator, PJM, and the distribution system is overseen by the state’s utilities.
  • Electric Distribution Company (EDC): Synonymous with “utility,” specifically referring to the local utilities that deliver electricity.
  • Front-of-the-Meter (FTM): Energy resources located on the utility side of the customer meter and connected directly to the distribution grid or transmission system. These resources supply electricity or grid services to wholesale markets, utilities, or multiple utility customers. Utility-scale solar projects, battery energy storage systems, and wind farms are examples of FTM resources.
  • Grid Reliability: The electric system’s ability to consistently deliver safe, dependable power while minimizing outages.
  • Grid Services: An umbrella term for a range of functions that support the grid; functions that keep the electric grid reliable, balanced, and cost effective. Grid services can support both the transmission and distribution grid. Examples include reducing demand during peak periods, keeping voltage and frequency stable, and relieving congestion on local lines. NOTE: Some entities (e.g. PJM) may have a more specific definition, so the meaning can depend on the context in which the term is used.
  • Grid Utilization: A measure of how much of the electric grid’s available capacity is actually being used to move and deliver electricity. Higher grid utilization generally means existing transmission and distribution infrastructure is being used more fully, while lower utilization can indicate that parts of the grid are underused. Very high utilization can also indicate congestion or limited remaining capacity at certain times or locations.
  • Integrated Resource Planning (IRP): A long-term planning process primarily used in vertically integrated, traditionally regulated electricity markets, where utilities are responsible for planning and procuring the resources needed to cost-effectively meet future customer demand while maintaining reliable service. IRPs evaluate different combinations of energy resources, including fossil fuel power plants, nuclear energy, renewable energy, demand-side management, and energy storage, while considering costs, reliability, environmental impacts, and public policy goals. Maryland does not utilize an IRP process, although the recent creation of the state’s Strategic Energy Planning Office (SEPO) is meant to oversee the function of creating a state energy plan.
  • Interconnection: The process of connecting new electricity generation or energy storage resources to the electric grid. The interconnecting utility, PJM, or both review interconnection applications to ensure the new system can operate safely and reliably without disrupting electric service. Depending on the size and complexity of the project, this review often requires engineering studies or grid upgrades financed by the owner of the system before the system can begin operating.
  • Levelized Cost of Energy (LCOE): The average cost of producing one unit of electricity over a generating system’s expected lifetime. It accounts for costs such as construction, financing, fuel, operations, maintenance, and expected electricity production, allowing different generation technologies to be compared on a consistent dollars-per-megawatt-hour basis. LCOE is a vetted, and widely used metric employed by institutions like Lazard in their annual Levelized Cost of Energy+ report.
  • Levelized Avoided Cost of Energy (LACE): A measure of the value that an electricity generating resource provides to the power system over its lifetime. It estimates the cost the grid would otherwise incur to produce the same electricity and capacity if that resource were not built, expressed as an average cost per unit of electricity. LACE is often compared with the LCOE: if a resource’s LACE is higher than its LCOE, the value it provides to the grid is greater than its estimated cost.
  • Levelized Full System Cost of Electricity (LFSCOE): A metric that estimates the cost of serving an entire electricity system using only one type of generation, supplemented by energy storage. Unlike traditional levelized cost measures, it assumes that the selected technology replaces all other generation resources and must meet demand around the clock. LFSCOE is a non-mainstream metric based on an unrealistic single technology scenario that does not reflect how PJM and other wholesale markets dispatch a diverse generation fleet.
  • Net Energy Metering (NEM): A billing arrangement that allows utility customers with on-site generation to offset electricity purchased from the grid with electricity exported by their system during the same billing period. Under Maryland’s existing NEM program, exported electricity offsets grid consumption on a 1:1 kilowatt-hour basis, meaning these customers are credited by the utility for the electricity they generate at the same retail rate they are charged for electricity. Any unused excess generation may be carried forward as a credit to offset electricity consumed on later utility billing periods. Maryland also uses NEM-based bill credits for community solar subscribers. The existing program remains available until the earlier of July 1, 2027, or the statewide total reaching 3 gigawatts, with limited exceptions for certain community solar projects.Following passage of the Utility RELIEF Act of 2026, the Public Service Commission (PSC) is considering changes to Maryland’s NEM rules, including the transition to a successor program, grandfathering requirements, statewide capacity tracking, time-varying rates, and aggregate net metering. This rulemaking is also examining compensation for exported electricity, ratepayer costs and benefits, and the treatment of different generation technologies and market segments.
  • Peak Demand: The highest level of electricity use during a specified period, often occurring during very hot summer afternoons or cold winter mornings. Because the electric system must have enough generation and grid capacity available to meet this maximum demand, peak demand significantly influences electricity costs, resource adequacy requirements, and long-term infrastructure planning. DERs that reduce or shift electricity use during peak periods can thus support grid reliability, lower electricity costs, and defer infrastructure investments. PJM is responsible for ensuring the grid can meet peak demand. Their peak demand forecasting has been affected by massive data center demand projections. In 2024, growing electricity demand, particularly from data centers, combined with changes to market rules, contributed to an 800% increase in PJM’s capacity auction prices, which led to rising electricity bills for customers across the region.
  • PJM Interconnection: The regional organization responsible for operating the high voltage transmission system and the wholesale electricity market in 13 states and the District of Columbia. PJM controls the process for determining when and how new large generation resources can connect to the transmission system. Historically, that process was a major bottleneck: PJM accumulated a large backlog of proposed generation projects and some resources have faced years of studies, repeated delays, and uncertainty about the cost of grid upgrades, before the resource can interconnect and begin operating. PJM has since overhauled its interconnection process, but lengthy and complex interconnection remains a significant challenge to bringing new generation online. PJM’s voting structure gives significant influence to utilities, electricity generators, transmission owners, and other energy market participants. These entities collectively represent four of PJM’s five voting sectors, while end-use customers, including consumer advocates, share the remaining sector. State utility regulators can participate in PJM’s stakeholder process but do not have voting rights. This means that the companies participating in PJM’s electricity markets also have substantial influence over the rules governing those markets.. The Federal Regulatory Energy Commission (FERC) oversees PJM, and is considering governance reform to address some of these issues.
  • Power Purchase Agreement (PPA): A contract under which a customer, utility, or other buyer agrees to purchase electricity from an energy project at specified prices and terms for a set period. PPAs provide the project owner with a predictable revenue stream and allow the buyer to secure electricity without owning the generating system.
  • Resource Adequacy: Having enough available energy resources to meet customer demand during periods with the highest electricity use (see Peak Demand).
  • Transmission System (sometimes referred to as “The Grid” or “Transmission Grid”): The network of high voltage power lines, substations, transformers, and related equipment that moves large amounts of electricity over long distances between large power plants and local distribution grids. Regional transmission organizations such as PJM coordinate transmission operations and planning across multiple states to maintain reliability.
  • Virtual Power Plant: A network of DERs coordinated through software to operate collectively and provide grid services comparable to those of a traditional power plant. VPPs can reduce or shift electricity demand and supply electricity to the grid when needed. Typically, VPPs are more dynamic and can include generation and storage assets (e.g. a home battery or solar system), as well as tools that reduce load (e.g. demand side management).
Back to Top

Renewable Energy and Demand Side Management

  • Alternative Compliance Payment (ACP): A fee that a Maryland electricity supplier pays for each megawatt-hour by which it falls short of the state’s Renewable Portfolio Standard (RPS), instead of retiring the required Renewable Energy Credit (REC) or Solar Renewable Energy Credit (SREC). ACPs are deposited into the Maryland Strategic Energy Investment Fund and help place an effective ceiling on REC prices because suppliers may pay the ACP when credits are unavailable or more expensive. In 2024, the Maryland PSC recorded $365 million in ACP costs, which are recovered from customers through electricity supply charges.
  • Beneficial Electrification: The replacement of fossil fuel technologies with electric alternatives when doing so lowers overall costs and improves efficiency.
  • Demand Response: Programs or market arrangements that reward customers for reducing or shifting their electricity use during periods of high demand, high prices, or grid stress. Participants may respond manually or through automated controls, helping reduce peak demand and avoid the need to operate or build additional generation or grid infrastructure. Demand response is an example of demand side management.
  • Energy Efficiency: Using less energy to provide the same or better level of service, comfort, or productivity. Examples include efficient lighting and appliances, improved insulation, high efficiency heating and cooling systems, and industrial equipment that reduces energy waste. Energy efficiency is also a type of demand side management.
  • Energy Storage Technologies: Absorb electricity or another form of energy and release it later when needed. Batteries are the most common form of modern electric storage, but other examples include pumped hydropower, thermal storage, and flywheels. Storage can shift electricity from lower demand periods to higher demand periods, provide backup power, reduce peak demand, and support grid reliability.
  • Energy Storage Market Segments
    • Behind-the-Meter (BTM) Energy Storage: A storage system located BTM that can provide backup power, reduce electricity purchases during high cost periods, manage peak demand, or store electricity produced by on-site generation such as rooftop solar. They may also participate in utility programs or VPPs that combine multiple customer owned resources to provide grid services.
    • Distribution-Connected Energy Storage: A Front of the Meter (FTM) storage system connected directly to the distribution grid. These projects can relieve local grid constraints, support distribution-system reliability, complement distributed generation such as community solar, and provide energy, capacity, or other grid services.
    • Utility Scale/ Transmission-Connected Energy Storage: A large Front of the Meter (FTM) storage system connected to the high voltage transmission system and operated primarily to serve the broader electric grid. These projects may participate in wholesale energy, capacity, and ancillary services markets, reduce transmission congestion, integrate large amounts of renewable generation, and support regional reliability.
    • Stand-Alone Energy Storage: A storage system developed and operated independently of a specific generation facility. It charges from the electric grid and can be located where its services are most valuable, such as near constrained substations, large loads, or transmission facilities.
    • Generation-Coupled Energy Storage: A storage system paired with a generation resource so that electricity produced by the generator can be stored and delivered later (e.g. solar + storage). Coupled storage can smooth variable output, provide more predictable delivery of electricity, and shift electricity generated from renewable energy resources to higher demand periods. Depending on the project’s design and interconnection agreement, the storage system may charge only from the paired generator or may also charge from the grid.
  • Renewable Energy Credit (REC): A tradable certificate representing the renewable energy attributes of one megawatt-hour of electricity generated by an eligible renewable energy resource. In Maryland, electricity suppliers purchase and retire RECs from Tier 1 and Tier 2 resources to meet Maryland’s
  • Renewable Portfolio Standard (RPS): The REC may be bought and sold separately from the electricity itself.
  • Solar Renewable Energy Credit (SREC): A type of REC created by eligible solar generation at the rate of one SREC for each megawatt-hour produced. Electricity suppliers use SRECs to satisfy the solar specific portion, also known as the “solar carve out,” of Maryland’s RPS, creating an additional source of revenue for whoever owns the credit.
  • Solar Technologies: Convert sunlight into electricity using photovoltaic panels or capture the sun’s heat for thermal energy applications. Solar generation has no fuel cost, and although output varies with weather and time of day, the energy generated follows predictable daily and seasonal patterns. Solar technologies are commonly grouped into market segments based on system size, location, and customer type.
  • Solar Market Segments
    • Behind-the-Meter (BTM) Solar: A solar system located on a customer’s property and used primarily to offset electricity consumed by that customer. It may serve a home, business, farm, institution, or industrial facility, and any excess electricity is exported to the grid under applicable Net Energy Metering (NEM) rules.
    • Aggregate Net Energy Metering (ANEM) Solar: A solar arrangement that allows a single customer to allocate excess generation credits among multiple electric meters or accounts associated with that customer. In Maryland, ANEM is available to agricultural customers, nonprofit organizations, municipal and county governments and their affiliated organizations, state government agencies, and higher education institutions. Unlike community solar, it combines accounts associated with a single eligible customer.
    • Community Solar: A Front of the meter (FTM) solar system connected to the distribution grid that allows multiple customers to subscribe to a share of the system’s output and receive credits on their electric bills without having to install solar on their own properties. Under current Maryland law, a community solar system must be located in the same electric utility service territory as its subscribers, have at least two subscribers, and may not exceed 5 megawatts of capacity. Community solar projects are commonly ground-mounted but may also be located on rooftops. Maryland’s law requires at least 40% of power produced by a community solar project to go to low-to-moderate income households, and also guarantees financial savings for all residential community solar subscribers.
    • Utility Scale Solar: A large, usually ground-mounted, front of the meter (FTM) solar system that is normally connected to the transmission system and supplies electricity to the broader electric grid. These projects sell electricity through wholesale market participation, a power purchase agreement (PPA), or another market arrangement.
  • Tier 1 Renewable Sources: The primary category of energy resources eligible under Maryland’s Renewable Portfolio Standard (RPS). Tier 1 includes energy resources from solar, wind, methane, geothermal, ocean energy, certain fuel cells, small hydroelectric facilities, poultry litter, thermal biomass, and wastewater used for heating or cooling.
  • Tier 2 Renewable Sources: A separate category under Maryland’s Renewable Portfolio Standard (RPS) consisting of hydroelectric power other than pumped storage generation. Maryland requires electricity suppliers to meet a 2.5% Tier 2 requirement, although Tier 1 renewable energy credits may also be used to satisfy that requirement.
Back to Top

Utility Regulation and Markets

  • Ancillary Services: The specialized services that keep the electric grid operating safely and reliably, including balancing electricity supply and demand, maintaining the grid’s frequency and voltage, and providing backup power when unexpected events occur. Traditionally supplied by large power plants, ancillary services are increasingly provided by Distributed Energy Resources (DERs) and other advanced technologies.
  • Capacity Markets: Organized electricity markets that pay power plants, energy storage, demand response, and energy efficiency resources to help meet future electricity demand, even if they are not producing electricity every day. In Maryland, the capacity market is administered by PJM through its Reliability Pricing Model. Its purpose is to help ensure the power system has enough reliable capacity to meet peak demand, reduce the risk of shortages, and maintain reliability during periods of high system stress. The prices set through PJM’s capacity auctions ultimately affect the cost of electricity paid by Maryland customers.
  • Competitive Electricity Market (aka Restructured or Deregulated Market): An electricity market in which customers may choose their electricity supplier instead of being required to buy power from their local utility. The utility still owns and operates the distribution system and delivers the electricity to customers, while competitive suppliers sell the electricity itself. Customers who do not select a supplier receive utility provided default service. In these markets, electricity prices are determined through competition rather than by regulators alone. Maryland has a deregulated electricity market.
  • Cost Recovery: The process by which utilities recover the reasonable costs of providing electric service through customer rates approved by the Maryland Public Service Commission (PSC), including investments in power lines, substations, maintenance, and other infrastructure needed to operate the electric system.
  • Default Service Rate: The price charged by a utility for electricity supply when a customer does not independently shop for a competitive electricity supplier. In Maryland, the utility purchases this electricity on customers’ behalf and passes the approved supply costs through without earning a profit on the energy itself.
  • Rate Design: The process of determining how utilities charge customers for electricity. Electric rates include a combination of fixed charges, charges based on the amount of electricity used, and, for some customers, charges based on their highest level of electricity demand. Rate design that prioritizes ratepayer needs seeks to recover utility costs while encouraging efficient energy use and maintaining fair treatment among different customer groups.
  • Standard Offer of Service: The price charged by a utility for electricity supply when a customer does not independently shop for a competitive electricity supplier. The utility purchases this electricity on customers’ behalf and passes the approved supply costs through to customers, along with approved administrative charges that may include a utility profit.
Back to Top

Emerging Technologies and Policy Concepts

  • Advanced Transmission Technologies (ATTs): Technologies that increase the capacity, efficiency, reliability, or flexibility of the existing high voltage transmission system. Examples include advanced conductors, dynamic line ratings, power flow control devices, and improved monitoring systems. By allowing more electricity to move over existing infrastructure, these technologies accelerate the interconnection of new sources of generation and defer, reduce, or sometimes avoid the need to build costly new transmission lines.
  • Flexible Interconnection: Allowing a generation source to connect to the grid subject to agreed operating limits, rather than requiring the grid to accommodate the project’s full output at all times. For example, a utility may temporarily limit a solar or battery system’s exports when local grid capacity is constrained. This approach reduces or avoids costly grid upgrades needed to interconnect the system, thus allowing projects to begin producing electricity more quickly. The customer assumes some risk that the system’s output may occasionally be restricted. Maryland utilities have begun using flexible interconnection methods to accommodate more Distributed Energy Resources (DERs) on the distribution grid.
  • Grid Enhancing Technologies (GETs): Technologies that help grid operators use existing electric infrastructure more efficiently, safely, and reliably. The term is commonly used interchangeably with ATTs but GETs are also applied to improving the operation of the local distribution grid. Distribution grid improvements include advanced sensors, smart meters, automated controls, communications systems, cybersecurity measures, and advanced distribution management systems. By increasing usable distribution grid capacity and reducing congestion, these technologies can connect Distributed Energy Resources (DERs) more quickly and defer or avoid costly infrastructure upgrades.
  • Grid Modernization: An umbrella term encompassing efforts to upgrade the transmission system or distribution grid with new technologies and operating practices that improve reliability, efficiency, resilience, security, and the ability to cost effectively integrate new sources of electricity generation. Simply put, grid modernization refers to “getting more out of the grid we have.”
  • Microgrids: Small, self-contained electric networks that can generate, store, and distribute electricity to a specific group of buildings or facilities, such as a hospital, military base, university campus, or neighborhood. A microgrid operates while connected to the larger electric grid but can disconnect and continue providing power during outages, improving resilience and reliability.
  • Vehicle-to-Grid Technology (V2G): Allows electric vehicles to both charge from the distribution grid and send electricity back to the grid when needed. By using the vehicle’s battery as a temporary energy resource, V2G can help reduce peak demand, improve grid reliability, and support the integration of renewable energy. Vehicle owners may also receive financial compensation for participating in V2G programs.
Back to Top

This glossary was prepared by Labora Strategies, LLC for the Maryland League of Conservation Voters Education Fund. Labora Strategies is led by Leah Meredith, a Maryland-based energy policy and programs professional with more than a decade of experience working across the PJM and MISO markets. Her background includes designing and implementing policies and utility programs focused on affordability, service delivery, and grid reliability in partnership with utilities, public entities, advocacy organizations, and independent power producers.

2026-10-16T09:30:27-04:00October 16th, 2026|Categories: Clean Energy & Energy Efficiency|

Electric School Buses Blog – September

In September, the Maryland League of Conservation Voters of Maryland Education and Chispa Maryland continued working toward bringing more electric school buses to our state.

The highlight this month occurred in Montgomery County, where a Chispa Maryland Community Leader spoke in front of the Board of Education on September 24.

Veronica Carreto testified in support of the county’s continued transition to electric school buses. Chispa Maryland mothers, students, and leaders collected 435 petition signatures (!) calling on the Board to apply for a Maryland Energy Administration (MEA) grant to support the transition. Other Chispa Maryland leaders also attended the meeting to stand with Veronica and show community support for cleaner, healthier transportation for students.

CHISPA Maryland continued advancing our “Clean Buses for Healthy Kids” campaign through community engagement activities, including back-to-school events, community fairs, outreach tables, one-on-ones, and other events throughout the counties where we organizing!

These activities provided opportunities to continue raising awareness, educating, and engaging families about the importance of electric school buses and the benefits they can provide for children, families, and communities.

In addition, one of the primary efforts in recent months was increasing accountability with the Baltimore City Board of School Commissioners, and that continued in September. Chispa coordinated outreach to Board members and BCPS stakeholders and continued asking the district to establish clear goals and timelines for future electric school bus purchases and pursue available MEA funding. Chispa also continued engaging partners and stakeholders around Maryland’s Medium-Duty and Heavy-Duty Zero-Emission Vehicle Grant Program and sharing information about available funding opportunities that could support school bus electrification.

Maryland has been a national leader in electric school buses, and the Maryland LCV Education Fund and Chispa Maryland are working to ensure those electric school bus wheels keep turning!

2026-10-08T16:26:34-04:00October 8th, 2026|Categories: Electric-School-Buses, Our Work|

Utility Accountability

Photo by Jordan Drumm | Used by permission

Maryland League of Conservation Voters Education Fund (MD LCVEF) is a proud member of Upgrade Maryland.

Upgrade Maryland works to upgrade Maryland’s homes and businesses with the most efficient electric equipment and healthy building standards that will keep bills low, safeguard our health, and help meet our climate goals.

It’s up to our utility regulators at the Maryland Public Service Commission to protect residents from unnecessary rate hikes to pay for this methane gas spending and jumpstart an equitable transition to clean heat.

Maryland LCV Education Fund supports a strong outcome from the PSC’s Future of Gas Proceeding to manage an intentional and planned transition off the gas system. Changing gas utility planning and operations are necessary to align with Maryland’s climate goals. The state aims to reduce greenhouse gas emissions 60% by 2030, and achieve net zero emissions by 2045.

See the Upgrade Maryland Action Guide for the Maryland Public Service Commission public hearing on the Future of Gas here.

Upgrade Maryland is calling on utility regulators to protect consumers by engaging in strategic planning for the future of our gas system.

By joining the 12 other states engaging in strategic gas system planning, Maryland utility regulators can direct investments wisely in the projects that will lower energy bills, keep Marylanders safe, clean up our air, deliver more comfortable homes, and reduce climate pollution from our buildings.

We’re working to educate the public about the proceedings and make sure the PSC hears from community voices, including consumer advocates, environmentalists, public health professionals, and faith leaders, as they engage in strategic planning with gas utilities.

2026-11-02T08:02:25-05:00October 8th, 2026|Categories: Clean Energy & Energy Efficiency|

Clean Heat

Maryland Clean Heat Coalition

Maryland League of Conservation Voters Education Fund (MD LCVEF) is a proud member of the Maryland Clean Heat Coalition (MCHC). 

The MCHC works to advance policies to help residents equitably upgrade to healthier, more affordable homes. Educating people about utility affordability through clean energy is central to MD LCVEF’s mission. Maryland residents today rely on inefficient, polluting equipment that results in billions in health costs each year, drives up energy bills, and undermines our climate goals. By upgrading homes with clean, efficient, state-of-the-art systems, Maryland can deliver cleaner air, affordable energy, and healthier communities.

Maryland LCV Education Fund is committed to supporting a healthy environment for everyone in Maryland, which includes both indoor and outdoor air pollution. We are working with the Clean Heat Coalition to support strong state Clean Heat Rules, including a Clean Heat Standard and Zero Emissions Heating Equipment Standard.    

Learn more about MCHC here. 

2026-10-08T16:15:04-04:00October 8th, 2026|Categories: Clean Energy & Energy Efficiency|

Electric School Buses August Event Roundup

The Chispa Maryland team was busy in August, talking about electric school buses and the benefits they can bring to students, parents, and school districts.

Morena started the month meeting and greeting at the National Night Out on August 4th in Colmar Manor, Prince George’s County.

Morena then went to the Colmar Manor Back to School event at the invitation of Colmar Manor Mayor Monica Casañas on August 13th. At both events in Colmar Manor, Morena and Promotoras met with numerous parents and discussed how electric school buses keep kids healthy in their critical developmental years.

A few days earlier, on August 12, Chispa Maryland hosted an Electric School Bus Town Hall, attended by Baltimore City School Board Commissioner Ashley Esposito. The event featured a presentation by Ramón Palencia-Calvo, Chispa Maryland Senior Director, on Electric School Buses. Watch messages from the event by a pair of Promotoras and Ashley Esposito HERE.

On the 19th, Morena visited the ever-popular Crossroads Farmers Market, in Takoma Park, Montgomery County for their “Back to School Bash” letting attendees know about the availability of funds for electric school buses.

The very next night, Morena, Eliseo and several Promotoras joined other Maryland LCV staff for the latest edition of Green Drinks Annapolis. In addition to some live music, folks heard from Natalie Buscemi, the Transportation Program Manager at the Maryland Energy Administration and Claire Alford, the Senior Eastern Regional Manager of Market Development at Highland Electric Fleets. Natalie and Claire shared their unique perspectives on electric school buses.

On August 22, CHISPA Maryland hosted a Solar-Powered Back-to-School Fair at Patagonia Baltimore, where over 100 community members and families learned about the electric school bus campaign and how to take action. Together, these efforts demonstrate CHISPA Maryland’s commitment to building community leadership and advancing environmental justice so every Baltimore City student can learn and travel in a clean, healthy, equitable environment for all.

On August 24, Morena returned to Takoma Park, where she visited Rolling Terrace Elementary School and spoke to parents about electric school buses, encouraging them to sign the petition that will urge their school district to apply for publicly available funding.

Eliseo rounded out the month by attending his second listening session hosted by new Baltimore City Schools CEO Dr. Jermaine Dawson. This was a follow-up to the initial session in late July, which Eliseo and several Promotoras attended. The listening sessions are opportunities for parents, students, educators, and community partners to let their voice be heard.

“It was encouraging to hear about their vision and priorities for building stronger schools for every student,” Eliseo said.

He continued:

“We were proud to be part of the conversation and to remind district leaders that environmental justice must also be a priority. Every child deserves to learn in a healthy environment with clean air, safe school buildings, and access to clean transportation, including electric school buses.

“We’re grateful for the opportunity to make sure environmental justice was part of the discussion, and we look forward to continuing to work together to create healthier, stronger schools for all Baltimore City students.”

Know about the latest electric school bus news by following Chispa on Facebook, as well as the Maryland LCV pages on Facebook and Instagram.

2026-09-11T10:56:22-04:00September 11th, 2026|Categories: Blog, Our Work|

My Summer Internship

By Calvin Chrisfield

Calvin ChrisfieldThis summer, I had the pleasure of interning with the Maryland League of Conservation Voters Education Fund through the University of Maryland’s Do Good Impact Interns program. This was a fantastic experience that taught me so much about working in the environmental policy space and gave me valuable skills that I will bring with me as I complete my education and begin my career.

Going into this internship, I was thrilled at the opportunity to work with the Maryland LCV Education Fund. Through my public policy background and previous experience in the Maryland environmental policy space, I was familiar with Maryland LCV Education Fund’s work, and their reputation preceded them. I was honored to be given this opportunity to work with such a well-respected team and apply my public policy education to make a real-world difference. 

Upon joining the team, I quickly learned that Maryland LCV Education Fund lived up to their reputation. I was able to work with some of the most passionate and politically savvy people I have ever met, learning every day to be a better environmental advocate. 

The highlight of this experience was the opportunity to work on the Environmental Justice Storytelling Project. This project allowed me to tell the stories of several environmental justice leaders from across the state who have worked to make their communities a safer, cleaner, more sustainable place. Learning from these advocates has been incredibly inspiring, and it has been an honor to uplift their voices and tell their stories. You can read all of these stories here.

To any future Maryland LCV Education Fund interns, I’d love to leave a few pieces of advice. First, try to come into the office whenever you can. One of the best parts of this internship is the opportunity to meet and learn from the Maryland LCV Education Fund team, so make sure you take advantage of that opportunity whenever possible. Second, if you have something valuable to add to a conversation, add it. You are going to come into this internship with your own unique knowledge and experiences, so don’t be afraid to share that with the rest of the team when it applies. Finally, you will get out of this program what you put into it, so dive in headfirst. If you engage fully and allow the mission to inspire you, you will have a fantastic summer full of learning. 

Calvin is studying public policy at the University of Maryland and expects to graduate in 2027. You can find his LinkedIn here.

2026-09-03T14:13:36-04:00September 3rd, 2026|Categories: Blog|

Planning for Electric School Bus Deployment

Maryland is building the Foundation for This Transition

2019

School Bus Transition (HB 1255)

  • Directs MDE and MDOT to provide technical assistance to school districts and contractors to plan and deploy electric school buses and charging infrastructure.

2022

Climate Solutions Now Act (SB 528)

  • Requires school districts to purchase only zero-emission buses starting in 2025 (with technology and funding waivers).
  • Establishes a utility electric school bus pilot program covering incremental administrative and operating costs.

Electric School Bus Funding

Funding Source & RoundLaunch YearAmount
EPA Round 1 (Rebates)2022$965,000,000
EPA Round 2 (Grants)2023$965,000,000
EPA Round 3 (Rebates)2023$900,000,000
Maryland VW Trust2019$2,500,000
Maryland MDE Grant2024$3,000,000
Maryland MEA FY252024$12,000,000
Maryland MEA FY262025$4.900,000
Maryland MEA FY27 (MHD-ZEV)2026$12,500,000

2026-09-11T11:02:38-04:00September 1st, 2026|Categories: Our Work|
Go to Top